BPTT Commences Gas Production From Savonette Field Off Trinidad
Published: 28-Oct-2009
BP Trinidad and Tobago (BPTT) has announced the start of natural gas production from the Savonette field, offshore Trinidad & Tobago. Savonette is located in 290 feet (88 metres) of water around 50 miles off Trinidad's south east coast. BPTT holds a 100% interest in the field.
Production from the platform is tied into BPTT's Mahogany B platform, via a 26-inch diameter 5.3 mile subsea pipeline, where the gas is processed and then exported into BPTT's existing infrastructure. Gas from Savonette will supply Atlantic LNG's liquefaction plant for export as LNG to international markets, as well as the domestic market.
With Savonette, BPTT now has production from 12 offshore platforms.
Production from Savonette is expected to average 600 million standard cubic feet per day of gas, plus associated condensate, from four wells. Savonette production will contribute to maintaining bpTT's total production level at more than 450,000 barrels of oil equivalent a day.
The Savonette platform, installed in February 2009, is the fourth in a series of normally unmanned installations designed and constructed locally in Trinidad using a standardized 'clone' concept. The 1,898 tonne jacket and the 871 tonne topsides were built at the Trinidad Offshore Fabricators (TOFCO) yard in La Brea, south Trinidad.
BPTT's Chairman and Chief Executive Officer Robert Riley said: "Since completing the Cannonball platform in 2005, in just four years bpTT has designed and constructed three further platforms right here in Trinidad and commenced production from each - Mango, Cashima and now Savonette. I am very proud of bpTT's sustained track record in managing projects of this magnitude and with such tight timelines - designing, constructing and producing from four platforms in four years is a great achievement."
The Savonette platform has high Trinidadian local content with some 30 per cent of its total engineering, procurement and construction value being spent in country and with T&T nationals being responsible for 55 per cent of the project management hours and 98 per cent of total fabrication hours.
Savonette Project Manager Liz Mulliss noted: "The project has progressed safely without any lost-time incidents. BPTT has now operated for just over 12 million manhours without a lost-time incident."
Network Sites

Suppliers To This Sector
Browse A-Z
Addleshaw Goddard
Energy and Utilities UK Law Firm ...
Applus RTD
Non-Destructive Testing, Inspections and Asset Integrity Management ...
ATI Stellram
High-Performance Metal Cutting Tools ...
BBC Chartering
Break Bulk and Heavy Lift Shipping ...
Bea Technologies SpA
Filtration Technology ...
Beluga Shipping
Your Experts for Heavy Lift and Project Cargo ...
White Papers
Browse A-Z
2.5MW Wind Turbine
The latest evolution of GE Energy’s wind turbine technology, the 2.5xl wind turbine, is pl ...
Hardcore® Technology Drilling Solutions for the Heat Exchanger Industry
ATI Stellram develops and produces high-performance metal cutting tools for difficult-to-m ...
Annual Report 2008
IBERDROLA Engineering and Construction has extensive experience in this field, acquired as ...
Increasing Cost-Efficiency of Substation Automation Systems by Centralised Protection Functions
New legislative and customer-oriented requirements pose challenges to substation automatio ...
Applying Modern Communication Technology to Loss-of-Mains Protection
The protection of distribution networks is facing new challenges from an increasing amount ...
Impacts of Quality Improvement Incentives on Automation Investments in the Finnish New Regulation Model
During the second regulatory period of 2008-2011 incentives are included into the Finnish ...


Delicious
Digg
Reddit
Stumble
LinkedIn
Mail sent successfully